SpaceX AI compute · promised vs delivered

1.7 GW

Promised vs delivered.

SpaceX had 1.7 GW at 30 Sep. It promised nearly 2.2 GW by 31 Oct (CFO, Q3 call; one transcript has "nearly 2") and 2.5 to 3 GW by 31 Dec. We check every date.

Nameplate compute, GW

30 Jun
1.4
30 Sep
1.7
31 Oct
~2.2
31 Dec
2.5–3.0

Solid = confirmed. Striped = promised. 30 Jun: SpaceX Q2 10-Q. 30 Sep and targets: CFO Bret Johnsen, Q3 2026 earnings call, 20 Oct (Motley Fool transcript).

Every promise, with receipts

PromiseDueConfirmed so far
Over 2 GW of AI compute by year end
SpaceX, Q2 call, 4 Aug 2026 · TSN Media recap of Q2 call
31 Dec 2026 On track
1.7 GW nameplate at 30 Sep (CFO, Q3 call). Target raised to 2.5 to 3 GW by end of Q4.
Nearly 2.2 GW nameplate by end of October (CFO, Q3 call; one transcript has "nearly 2")
CFO Bret Johnsen, Q3 call, 20 Oct 2026 · Q3 call transcript
31 Oct 2026 Check 31 Oct
1.7 GW at 30 Sep, plus "additional data halls already online in early October". No new total yet.
2.5 to 3 GW nameplate by end of Q4
CFO + Musk, Q3 call, 20 Oct 2026 · Q3 call transcript
31 Dec 2026 Check year end
Not yet. Needs +0.8 to 1.3 GW in Q4 from 1.7 GW at 30 Sep vs ~0.3 GW added in Q3.
Another 220k GB300 fully operational "next week" (week of 28 Sep)
Musk on X, 25 Sep 2026 · Elon Musk on X
~2 Oct 2026 Unconfirmed
Not confirmed as a single batch. On the Q3 call Musk said they are turning on about 200k to 220k GB300s a month.
Colossus 2 has 110k GB200 + 440k GB300
Musk on X, 25 Sep 2026 · Elon Musk on X
Stated as done Musk-said
Musk's own count. Not broken out in the 8-K or call.
Another ~220k GB300 in November
Musk on X, 25 Sep 2026 · Elon Musk on X
30 Nov 2026 Check November
Pending.
"If we get lucky", yet another 220k GB300 by late December
Musk on X, 25 Sep 2026 · Elon Musk on X
31 Dec 2026 Check year end
Pending. Conditional.
~110,000 GPUs delivered to Google by 30 Sep (contract)
SpaceX filing, 5 Jun 2026 · Reuters
30 Sep, grace to 31 Oct Check 31 Oct
Not disclosed in the Q3 release or call.
+10 GW in 2027 ("highly confident"), ~13 GW total by end 2027; 20 GW+ a "small possibility"
Musk, Q3 call, 20 Oct 2026 · Q3 call transcript
31 Dec 2027 2027
Long-dated.
440,000 Vera Rubin training cluster online
Musk, Q3 call, 20 Oct 2026 · Q3 call transcript
End of Q2 2027 2027
Long-dated.

Checkpoints

Sat 31 Oct 2026Nearly 2.2 GW? Google GPU grace period ends.
Mon 30 Nov 2026Another ~220k GB300 (Musk).
Thu 31 Dec 20262.5 to 3 GW nameplate. Over 2 GW year-end promise.

Updated 2026-10-22. "Musk-said" means a post or remark, not company guidance. Not financial advice. More dates: /catalysts.